Jan 16
Network Update

Peak demand is forecast at around 8400 MW with reserve supply of around 4400 MW.

 All lines are in service except:

  • U3 line – 330kv feeder line from Upper Tumut substation to the Snowy Hydro power station's switch yard. Crews have completed line assessment and are finalising work scope for repairs.  
  • 2 line from the Upper Tumut substation to Yass. Insulator repairs on three of six structures have been completed. Work will continue tomorrow.
  • 993 line (wood pole) 132kv from Gadara to Wagga Wagga is non-operational. The make safe work has been completed and five new steel structures have been delivered to sites. Work will continue tomorrow.

The Upper Tumut substation is operational and normal supply arrangements from Snowy Hydro Limited have been restored.