Overview

HumeLink is a new 500kV transmission line which will connect Wagga Wagga, Bannaby and Maragle.

It is one of the state’s largest energy infrastructure projects, with about 365 km of new transmission lines, and new or upgraded infrastructure at four locations.

Why do we need HumeLink?

To meet our future energy demands, Australia needs to transition to a greater mix of low-emission renewable energy sources, such as wind and solar. HumeLink will deliver a more reliable and more sustainable grid by increasing the amount of renewable energy that can be delivered across the national electricity grid, helping to transition Australia to a low carbon future.

Project update

Main construction has now started on HumeLink East and HumeLink West

The main construction works include construction of towers, building the new substations at Gugaa and Maragle, and upgrading existing substations at Bannaby and Wagga Wagga.

Transmission towers will be built in multiple stages from excavating and foundation construction to tower erection, followed by stringing of the transmission lines.

With the approvals in place, HumeLink East began work with the first pile bored near Tumut, while HumeLink West started vegetation clearing works in the Forestry portion of the alignment and is beginning foundation works at Gregadoo, east of Wagga Wagga.

Tower construction on HumeLink West through to the end of the year will progress from Wagga Wagga towards the south of Tarcutta, before progressing east to Ellerslie and Greenhills.

On HumeLink East, there will be multiple work fronts open from October. Work on tower foundations will be pushing north from Tumut towards the Murrumbidgee River. Crews will also be working on access tracks and tower foundations from the Yass area down to the Murrumbidgee River and from Bannaby towards Yass.

Some enabling works – which started in early 2025 – will continue, including access point establishment, access tracks and completion of the Kunama accommodation facility on HumeLink West.

Accommodation facilities at Tarcutta (HumeLink West) and Adjungbilly and Yass (HumeLink East) have been completed and have workers living on site.

Laydown facilities, which include equipment and materials storage, have been established at: Gugaa, Ellerslie, Maragle, Snubba Road and Batlow (HumeLink West), and Yass and Bannaby (HumeLink East).

Following consultation with community and stakeholders, additional laydown areas and concrete batching plant locations are being assessed at Lower Bago Road, Cullinga Park Lane, Honeysuckle Road and Gadara Road.

Local Business Register

We are interested in hearing from sole traders and businesses in the region that could provide a variety of products or services including engineering, design, general trades, administration, and Indigenous and support services. We’re also keen to hear from catering, accommodation, graphic design and printing services.

If you have a local business in the following Local Government Areas and are interested in working on the HumeLink Project, we would love to hear from you- simply complete our online form via the below link:

  • Upper Lachlan Shire
  • Yass Valley Council
  • Snowy Valleys Council
  • Cootamundra Gundagai Regional Council
  • Wagga Wagga City Council, or
  • Goulburn Mulwaree
  • Hilltops Council

The information collected will be shared with the HumeLink Delivery Partners and will be the project team’s first port of call when looking to procure goods and services.

Please note, registering your interest does not guarantee employment.

Timeline

  • Investigation of project options - Completed

    From 2019

  • Regulatory Investment Test (RIT-T) process - Completed

    From 2019, completed 2021

  • 1 km study corridor identified - Completed

    Early 2020

  • Community and landowner consultation - Completed

    Early 2020

    Community Consultative groups established late 2021

  • Environmental, field and technical studies - Completed

    From 2021 to 2023

  • Refined 200 m corridor announced - Completed

    Mid 2022

  • Secretary’s Environmental Assessment Requirements (SEARs) issued - Completed

    Mid 2022

  • Underground Feasibility Study - Completed

    Mid 2022

  • NSW Department of Planning and Environment’s public display of Environmental Impact Statement - Completed

    September - October 2023

  • Project Submissions Report and Amendment Report to NSW Department of Planning, Housing, and Infrastructure - Completed

    First half 2024

  • Planning approval obtained from State government - Completed

    November 2024

  • Planning approval obtained from Commonwealth government - Completed

    December 2024

  • Preparatory works, site establishment and early works - In progress

    Early 2025

  • Considered project status reached - Completed

    Mid 2025

    HumeLink is a Considered Project. To be classed as a Considered Project, the following conditions have to be met: necessary land and easements have to be acquired; all necessary planning and development approvals have to be obtained; the project has passed the Regulatory Investment Test for Transmission (RIT-T); and construction has either commenced or a firm date is set to commence.

  • Construction works starts on transmission lines and substations - In progress

    September 2025

  • Construction finishes - Proposed

    2027

Contact Us

  • Toll-free phone number: 1800 317 367
  • Email: humelink@transgrid.com.au 
  • Mail: HumeLink Community Engagement Team, PO BOX A1000, Sydney South NSW 1235
HumeLink

27 November 2025

Nation-critical HumeLink project marks major milestone as first towers rise

Australia’s transition to a clean energy future has taken a major step forward with specialist crews constructing the first of more than 800 new transmission towers on the nation-critical HumeLink project.

HumeLink

04 October 2025

Australia takes big step to more affordable clean energy with major construction underway on nation-critical HumeLink project

Australia’s transition to a clean energy future has taken another major step forward with the start of main construction works on HumeLink, one of the nation’s most important transmission infrastructure projects.

HumeLink

26 September 2025

Riverina and Snowy Mountains school students awarded HumeLink study scholarships

Twelve female high school students in the Riverina and Snowy Mountains are being awarded scholarships to supercharge their secondary education and support their journey towards future career success, thanks to Transgrid’s nation-critical HumeLink project.