Overview

HumeLink is a new 500kV transmission line which will connect Wagga Wagga, Bannaby and Maragle.

It is one of the state’s largest energy infrastructure projects, with about 365 km of new transmission lines, and new or upgraded infrastructure at four locations.

Why do we need HumeLink?

To meet our future energy demands, Australia needs to transition to a greater mix of low-emission renewable energy sources, such as wind and solar. HumeLink will deliver a more reliable and more sustainable grid by increasing the amount of renewable energy that can be delivered across the national electricity grid, helping to transition Australia to a low carbon future.

Project update

Main construction is in progress on HumeLink East and HumeLink West

The main construction works include construction of towers, building the new substations at Gugaa and Maragle, and upgrading existing substations at Bannaby and Wagga Wagga.

Transmission towers are being constructed in multiple stages, starting with excavation and foundation works, before progressing to tower erection and then stringing of the transmission lines.

Some enabling works – which started in early 2025 – will continue, including access point and access track establishment.

Accommodation facilities at Tarcutta and Kunama (HumeLink West), and Adjungbilly and Yass (HumeLink East) have been completed and have workers living on site.

Laydown facilities, which include equipment and materials storage, have been established at: Gugaa, Ellerslie, Maragle, Snubba Road and Batlow (HumeLink West), and Yass and Bannaby (HumeLink East).

Following consultation with community and stakeholders, additional laydown areas and concrete batching plant locations are being assessed at Lower Bago Road, Cullinga Park Lane, Honeysuckle Road and Gadara Road.

Timeline

  • Investigation of project options - Completed

    From 2019

  • Regulatory Investment Test (RIT-T) process - Completed

    From 2019, completed 2021

  • 1 km study corridor identified - Completed

    Early 2020

  • Community and landowner consultation - Completed

    Early 2020

    Community Consultative groups established late 2021

  • Environmental, field and technical studies - Completed

    From 2021 to 2023

  • Refined 200 m corridor announced - Completed

    Mid 2022

  • Secretary’s Environmental Assessment Requirements (SEARs) issued - Completed

    Mid 2022

  • Underground Feasibility Study - Completed

    Mid 2022

  • NSW Department of Planning and Environment’s public display of Environmental Impact Statement - Completed

    September - October 2023

  • Project Submissions Report and Amendment Report to NSW Department of Planning, Housing, and Infrastructure - Completed

    First half 2024

  • Planning approval obtained from State government - Completed

    November 2024

  • Planning approval obtained from Commonwealth government - Completed

    December 2024

  • Preparatory works, site establishment and early works - In progress

    Early 2025

  • Considered project status reached - Completed

    Mid 2025

    HumeLink is a Considered Project. To be classed as a Considered Project, the following conditions have to be met: necessary land and easements have to be acquired; all necessary planning and development approvals have to be obtained; the project has passed the Regulatory Investment Test for Transmission (RIT-T); and construction has either commenced or a firm date is set to commence.

  • Construction works starts on transmission lines and substations - In progress

    September 2025

  • Construction finishes - Proposed

    2027

Local Business Register

The HumeLink Project has moved into its construction phase, and continues to value the involvement of local businesses in supporting delivery. While many key packages are already in place, there are still opportunities for businesses to contribute to the project as needs arise.

We are particularly interested in businesses offering:

  • Engineering and technical services
  • Design and drafting
  • General trades
  • Administration and office support
  • Indigenous services

If you have a local business in the following Local Government Areas and are interested in working on the HumeLink Project, please complete our online registration form via the below link:

  • Upper Lachlan Shire
  • Yass Valley Council
  • Snowy Valleys Council
  • Cootamundra Gundagai Regional Council
  • Wagga Wagga City Council
  • Goulburn Mulwaree
  • Hilltops Council

The information collected will be shared with the HumeLink Delivery Partners and will be the project team’s first port of call when looking to procure goods and services.

Please note, registering your interest does not guarantee employment.

Contact Us

  • Toll-free phone number: 1800 317 367
  • Email: humelink@transgrid.com.au 
  • Mail: HumeLink Community Engagement Team, PO BOX A1000, Sydney South NSW 1235
HumeLink

18 December 2025

HumeLink announces $1.8 million in grants for local community groups

Seventeen community organisations along the HumeLink transmission line corridor have been awarded a total of $1.8 million in first-round funding for projects that will bring lasting social, economic and environmental benefits to the region.

HumeLink

27 November 2025

Nation-critical HumeLink project marks major milestone as first towers rise

Australia’s transition to a clean energy future has taken a major step forward with specialist crews constructing the first of more than 800 new transmission towers on the nation-critical HumeLink project.

HumeLink

04 October 2025

Australia takes big step to more affordable clean energy with major construction underway on nation-critical HumeLink project

Australia’s transition to a clean energy future has taken another major step forward with the start of main construction works on HumeLink, one of the nation’s most important transmission infrastructure projects.