In late 2021, Transgrid was asked by the community and landowners to investigate options which explore the feasibility of building the HumeLink project via underground cable instead of overhead transmission lines.
Transgrid agreed to form a collaborative, Steering Committee, which developed an underground feasibility study scope of works. GHD and sub-consultants Stantec were appointed due to their High-Voltage Direct-Current (HVDC) expertise.
Following the completion of additional independent reviews of the project costing assumptions, GHD and Stantec have finalised the HumeLink Project – Underground Report and the community members of the Steering Committee have provided Transgrid with their response to the Report. In February 2023 Transgrid released its response to the report.
The cost of undergrounding the HumeLink transmission lines is estimated to be $ 11.5 billion at least three times more than the entire project’s current cost of $3.3 billion.
This is unsustainable as the additional cost will be passed on to commercial, industrial and private electricity consumers, at a time of great concern about escalating electricity prices.
The additional expenditure would curtail expenditure on other transmission projects essential for connecting alternative, renewable energy to consumers. This is because there is only a finite amount of money available to rewire the nation to deliver alternative, renewable power.
Undergrounding transmission lines would mean a significant delay in completion of the project by up to five years.
This delay would threaten the timely connection of the new renewable energy and the related essential new interstate connections to the grid. It is essential that the infrastructure is completed by 2026 to secure the network before the ageing power stations are decommissioned. A significant delay would put the energy security and stability of large parts of Eastern Australia at risk of failure.
We understand and empathise with the concerns of landowners and their desire to avoid hosting transmission infrastructure on their land. We appreciate that people will be disappointed by the decisions following the completion of the report. However, it is very difficult to put in place any large infrastructure project without impacting some landowners. We hope that certainty may, to some extent, balance concern and disappointment.
Transgrid will continue to consult with landowners to minimise the impact to their properties.
Transgrid would like to acknowledge the efforts of the communities and volunteers from across the HumeLink footprint for the many hours they have contributed to the work of the steering committee since late 2021.